Conversion of existing building to hotel at bedford row, limerick
Conversion of an existing building to 12 bedroom Hotel and installation on a new stair and lift core. Works were completed over a 6-month duration. Throughout the works, the existing travel shop on the ground floor remained fully operational. Works included
- Construction of new lift and stair cores
- Lowering of basement floors
- Installation of mechanical, electrical, ventilation and lift
- Reconstruction of existing floors
- Installation of drylining and stud partitions
- Fire stopping works
- Flooring, tiling and decoration